S.No. Project Title Plot No Location Sector Nature of Case Status Covered Area (Sqft)
Street Block

SECTOR F-5

1. Gilgit Baltistan Counsel       F-5/1 Approval Work in progress 61014.00

SECTOR D-12

2.   6   Markaz D-12 Approval Work in progress 49138.00
3.   2   Markaz D-12 Approval Work in progress 72980.00
4.   12   Markaz D-12 Approval Work in progress 47000.00
5.   18   Markaz D-12 Approval Work in progress 31000.00
6.   11   Markaz D-12 Approval Work in progress 47000.00
7.   1   Markaz D-12 Approval Work in progress 73000.00
8.   30   Markaz D-12 Approval Work in progress 31000.00

SECTOR F-7

9.   01-C   Markaz F-7 Approval Work in progress 21547.00
10.   01-D   Markaz F-7 Approval Work in progress 37435.00
11.   04, C-III   Class-III F-7/2 Approval Work in progress 4500.00
12.   08, C-III   Class-III F-7/2 Approval Work in progress 4519.00

SECTOR F-8

13.   01, C-III   Class-III F-8/4 Approval Work in progress 11394.00
14.   14-W   Markaz F-8 Approval Work in progress 3746.00

SECTOR F-10

15. Sukh Chayan 06,   Markaz F-10 Approval Work in progress 421412.00
16.   02-D   Markaz F-10 Approval Work in progress 23000.00
17.   02-A   Markaz F-10 Approval Work in progress 23000.00
18. Park One 01   Markaz F-10 Approval Work in progress 1232713.48
19. Petrol Pump 03-A,   Markaz F-10 Approval Work in progress 1167.00
20.   03-A, C-III   Class-III F-10/4 Approval Work in progress 3780.00
21.   03-F, C-III   Class-III F-10/4 Approval Work in progress 3789.00
22.   05, Baz.05   Class-III F-10/4 Approval Work in progress 2244.00
23.   03-H, Baz.05   Class-III F-10/4 Approval Work in progress 3767.00

SECTOR F-11

24.   12   Markaz F-11 Approval Work in progress 36000.00
25. Shifa Hospital 05,   Markaz F-11 Approval Work not started 209959.00
26.   01-N, C-III   Class-III F-11/1 Approval Work not started 2880.00
27.   03, Eco-Flats   Economy Flats F-11/1 Approval Work not started 444400.00

BLUE AREA

28. Mall of Islamabad 56-N, Blue Area   Blue Area F-7/G-7 Approval Work in progress 528000.00
29.   B-3, Blue Area   Blue Area F-9/G-9 Approval Work in progress 141982.00
30.   C-3, Blue Area   Blue Area F-9/G-9 Approval Work in progress 141582.00
31.   23-E, Blue Area   Blue Area F-6/G-6 Approval Work in progress 33711.00
32.   04, Blue Area   Blue Area F-9/G-9 Approval Excavation of basement -
33. Elysium Mall 05, Blue Area   Blue Area F-8/G-8 Approval Work in progress 215240.00
34. Meezan Bank 3   Blue Area F-8/G-8 Approval Work in progress 248000.00
GRAND TOTAL COVERED AREA 6592872.00

BCS-II

S.No. Project Title Plot No Location Sector Nature of Case Status Covered Area Sqft
Street Block

SECTOR G-6

1.   Shop no. 648     G-6/1-4 Approval Work in progress 2740.00
2.   1-D   I&T G-6/1 Approval Work in Progress 9908.88

SECTOR G-7

3.   3-V     G-7 Markaz Approval Work in progress 18603.00
4.   3-G     G-7 Markaz Approval Work in progress 14635.00
5.   3-E     G-7 Markaz Approval Work in progress 17341.00
6.   3-D     G-7 Markaz Approval Work in progress 18186.81
7.   Masjid Syed-e-na Muhammad     G-7/4 Approval Work in progress 5531.48

SECTOR G-8

8.   28   I&T G-8/4 Approval Work in progress 10096.00
9.   7   I&T G-8/1 Approval Work in progress 20712.75
10.   3 Class-III Shopping Centre G-8/4-4 Approval Work in progress 4783.12
11.   3 Class-III Shopping  G-8/2-2 Approval Work in progress 4917.41
12.   59   I&T G-8/1 Approval Work in progress 20196.75
13.   25   I&T G-8/1 Approval Work in progress 6748.25

SECTOR G-9

14.   2-C Class-III Shopping Centre G-9/3   Work in progress 3810.06
15.   2-A Class-III Shopping Centre G-9/1   Work in progress 3799.06
16.   2-H Class-III Shopping Centre G-9/1   Work in progress 3094.06
17.   134   I&T G-9/1   Work in progress 10137.50
18.   40-E     G-9 Markaz   Work in progress 29918.50
19.   1-C Class-III Shoping Centre G-9/3   Work in progress 4030.37
20.   26-A     G-9 Markaz   Work in progress 64645.63
21.   1-B Class-III   G-9/1   Work in progress 4071.50

SECTOR G-10

22.   19   I&T G-10 Approval Work in progress 198881.71
23.   3-C Class-III Shopping Centr G-10/2 Approval Work in progress 3736.12
24.   3-D Class-III Shopping Centre G-10/3 Approval Work in progress 3980.67

SECTOR G-11

25.   20 Economy Flats G-11/3 Approval Work in progress 214799.01
26.   8 Economy Flats G-11/3 Approval Work in progress 215505.96
27.   12 Economy Flats G-11/3 Approval Work in progress 240511.46
28.   36 Hotel Hotel G-11 Markaz Approval Work in progress 334474.00
29.   30     G-11 Markaz Approval Work in progress 33866.74
30.   5 Class-III Shopping Centre G-11/3 Approval Work in progress 4008.75

H-SERIES

31.   4-O Community Core H-8/2     7664.45
32.   Jamia Masjid     H-11/4     15929.00
33.   7-A Class-III Shopping Centre H-11/4     7395.00
34.   Air University     H-11/2     254247.00
35.   18     H-9/1     29064.50
GRAND TOTAL COVERED AREA 1662972.00

BCS-III

S.No. Project Title Plot No Location Sector Nature of Case Status Covered Area Sqft
Street Block

SECTOR I-8

1.   11     I-8 Markaz Approval Work in progress 56695.00
2.   31     I-8  Markaz Approval Complete 61420.25
3.   30     I-8  Markaz Approval Complete 61574.42
4.   9     I-8  Markaz Approval Work in progress 56386.25
5.   36     I-8  Markaz Approval Work in progress 188686.83
6.   1-F Class-III   I-8/2 Approval Work in progress 5753.25

SECTOR I-9

7.   36, Industrial   Industrial I-9 Approval Work in progress 53985.54
8.   391, Industrial   Industrial I-9 Approval Work in progress 40445.00
9.   278-279, Industrial   Industrial I-9 Approval Work in progress 91033.70
10.   158, Industrial   Industrial I-9 Approval Work in progress 45512.63
11.   27, Industrial   Industrial  I-9 Approval Work in progress 77196.38
12.   137-C, Industrial   Industrial I-9 Approval Work in progress 21838.28
13.   47, Industrial   Industrial  I-9 Approval Work in progress 38326.22

SECTOR I-10

14.   9-B   Markaz I-10 Markaz Approval Work in progress 27057.24
15.   9-A   Markaz I-10 Markaz Approval Work in progress 26634.00
16.   190, Industrial   Industrial  I-10/3 Approval Work in progress 27935.00
17.   60-A   Industrial I-10/3 Approval Work in progress 23783.67
18.   82, Automobile   Workshop I-10/3 Approval Work in progress 1200.00

SECTOR I-11

19.   17   Whole Sale I-11/3 Approval Work in progress 8751.00
20.   02,    Cold Storage I-11/4 Approval Work in progress 46366.39
21.   02,    Truck Stand I-11/4 Approval Work in progress 5143.00

I.J.P Road

22.   8   I.J Principle Road     Complete 11495.00

I.T.K

23.   24   Indust I.T.K Approval Work in progress 105792.98
24.   15-E   Industrial I.T.K Approval Work in progress 5479.75
25.   51   Industrial I.T.K Approval Work in progress 17343.33

MARGALLAH TOWN

26.   1-H     M.T Ph-II Approval Work in progress 3789.00
27.   1-I     M.T Ph-II Approval Work in progress 3790.00

OTHERS

28.   Hascol Petrol Pump     Lohee Bher     8472.00
29.   Shell Pump     Jhangi Syedan     7100.05
30.   Kurri Road     Zone-IV     9456.54
31.   Software Export Board   NPA National Park Area     712331.39
32.   Koral Filling Station     Koral     6756.74
33.   Mouza Mira Bangal     Zone-IV     9091.00
34.   M/s. Attock Petroleum     Lohee Bheer     6689.07
GRAND TOTAL COVERED AREA 2114666.00