Capital Development Authority
Home | Contact Us
Major Projects In Progress
Last updated: 3rd Feb, 2017
Sr.
Project Name
Cost (Rs)
1.
Construction of interchange at Karal Intersection on Islamabad Expressway Islamabad.
1776.109 (M)
2.
Construction of interchange at Khanna and Sohan on Islamabad Expressway
2001.00 (M)
3.
Construction of 2nd Carriagweay from round about of Service Road (West) Sector G-10 to Khayaban-e-Iqbal, Islamabad.
235.842 (M)
4.
Dualization of Service Road (East) & (North) of Sector E-11 to Sector D-12, Islamabad
178.953 (M)
5.
Rehabilitation and re-carpeting of various roads in sectors of F&G series Islamabad.
845.232 (M)
6.
Improvement of Lane Marking for sectors F&G series, Islamabad
67.893 (M)
7.
Addition of three lanes on Kashmir Highway
3.526 (B)
8.
Construction of Bridge and Allied works in I-15/I-16
80.000 (M)
9.
Dualization of SR (North) I-10/I-11
70.702 (M)
10.
Development work in I-11/1and 2
180.00 (M)
11.
Construction of Bari Imam Complex
255.843(M)
12.
Construction of ICT Admin Block (I.G Block) in G-11
55.000 (M)
13.
Construction of 05 Nos. Police Barracks near K-Block
87.500 (M)
14.
Construction of SSP houses in H-11
85.500 (M)
15.
Development of walk in Aviary at Lake view park
79.421 (M)
16.
Construction of entertainment hub at Lake View Park
79.420 (M)
17.
Construction of 02 No police barracks in F-7, F-8
42.000 (M)
18.
Construction of Houses and sports complex in Police Academy H-11 (Balance work)
94.000 (M)
19.
Construction of Auditorium in Police Academy
78.527(M)
20.
Miscellaneous works in Police Academy
35.000 (M)
21.
Development works in Sector D-12
863.713 (M)
22.
Construction of 104 No family suits and 500s servant Quarters for Parliamentarians in sector G-5
2722.00 (M)
23.
Construction of 2nd hanger for Heliport
316 (M)
24.
Cost of police barracks Diplomatic Enclave
21.000 (M)
25.
SIS and AVC system in Senate Hall.
63.000 (M)
26.
Street lights in Sector G-13
90.000 (M)
27.
Construction of bridge in I&T Center G-9/4
65.000 (M)
28.
Street lights in Sector G-13
90.000 (M)
29.
Improvement of Ahmedia Grave yard, Sector H-9.
8.530 (M)
30.
Construction of Club House in sector F-6 Markaz Islamabad.
69.000 (M)
31.
Construction of Khayaban-e-Margallah from GT Road to Sector D-12, Islamabad. (Physical Progress: 51%)
588.428 (M)
32.
Dualization of Service Road East & North of Sector E-11 to Sector D-12, Islamabad. (Physical Progress: 49%)
178.953 (M)
33.
Construction of Citizen Club at Fatima Jinnah Park, F-9, Islamabad
1254.149 (M)
34.
Replacement of 15''dia sewerage lines from M.H 03 to 0-E in front of USA Embassy and 230 mm dia sewerage line from UAE embassy to Brazil Embassy M.H 102 to M.H 111, in Diplomatic Enclave Area, Islamabad.
2.558 (M)
35.
Rehabilitation of Sewerage line from COMSATS Building to Ex-US Aid Building and along Supreme Court Bar Building in Sector G-5, Islamabad.
3.781 (M)
36.
Replacement of damaged sewerage line from Cabinet Division to National Assembly and repair / raising of manhole in Sector G-5, Islamabad.
2.782 (M)
37.
Rehabilitation of sewerage line from Nusrat Hostel to Street # 08, Sector G-6/3 and Food Street in G-6 Markaz, Islamabad.
3.325 (M)
38.
P/L 9" dia sewerage line from Agha Khan Road to Street # 56, Abbas Market and Street # 53 to 54 in sector F-6/4, Islamabad.
3.334 (M)
39.
Rehabilitation of sewerage line from Buland Markaz to MCB in Blue area along Jinnah Avenue, Islamabad.
1.781(M)
40.
Rehabilitation of sewerage lines of created Plots between street No. 27 to 03 (IMCG) and street # 20 & 08 near Masjid-Al-Qasim SR (North) Sector G-10/2, Islamabad.
2.414 (M)
41.
Rehabilitation of defective & damaged sewerage lines along SP Office, G-10 Markaz, Islamabad.
1.633 (M)
42.
Rehabilitation of sewerage line from CDA Colony to street # 18 and repair of trunk sewer line in nullah in sector I-10/1, Islamabad.
3.471 (M)
43.
Rehabilitation of damaged portion of sewerage line near Masjid and laying of sewerage line from Mecho Plaza to Metro Cash & Carry, Sector I-11, Islamabad.
3.374 (M)
44.
Rehabilitation of damaged sewerage line from Street # 06 to main trunk sewer line (Pakistan Sweet Home) and from PTCL Building to SR (West), Sector H-9, Islamabad.
3.226 (M)
45.
Repairing / Raising of manholes slab and clearing of chocked sewerage lines at various locations in sector G-6/F-6 and Diplomatic Enclave Area, Islamabad (Petty works).
2.568 (M)
46.
Rehabilitation of sewerage line from Street # 6 to 4, Kohsar Market to St # 10 in sector F-6/3 and Street # 22 to 23 in sector F-6/2, Islamabad.
2.227 (M)
47.
Re-habilitation of sewerage lines St No. 01 to Gomel road Street No. 05, 04 and Shaheen Market in Sector E-7 Islamabad
2.169 (M)
48.
Rehabilitation of sewerage line from Margalla road to service road west in sector F-8/2 Islamabad.
1.067 (M)
49.
Rehabilitation of trunk sewer line along NDR,74% Dawn News (Zero point) Street # 33 and portion of70% trunk sewer line near Park in sector G-7/1, Islamabad.
2.613 (M)
50.
Rehabilitation of sewerage line street No. 16 Block No 27-A & 28-A in sector G-8/1 and Jhelum road in sector G-8/4 Islamabad.
2.306 (M)
51.
Rehabilitation of trunk sewer line on Ravi road H. No 310 to 343 in sector G-8/2, Islamabad.
1.787 (M)
52.
Rehabilitation of sewerage line from M. H.. # 36 to 64 and Bela road, in Sector G-10/1, Islamabad.
1.716 (M)
53.
Rehabilitation of defective sewerage lines at Gali No. 44 to 42, in Sector G-10/4, Islamabad.
0.767 (M)
54.
Rehabilitation of sewerage line along Crescent Plaza, Faysal Bank and Malik Plaza including repair of damaged manholes in F-10 markaz, Islamabad.
1.184 (M)
55.
Rehabilitation of sewerage line exchange to major road in F-11 markaz and street # 39, sector F-11/3, Islamabad.
1.110 (M)
56.
Rehabilitation of damaged sewerage line at VR-5 in I-8 markaz and street No. 69 & 53, in Sector I-8/3, Islamabad
2.395 (M)
57.
Up-Gradation / Rehabilitation of Fencing in Supreme Court Judges Enclave F-5 Islamabad.
3.500 (M)
58.
Rehabilitation/Improvement of Drainage system in Sectors of F&G Series Islamabad
27.371 (M)
59.
Construction and rehabilitation of footpaths in sectors F&G Series Islamabad
55.704 (M)
60.
Rehabilitation/Improvement of Signage & Painting of Kerb Stones of various sectors of F&G Series Islamabad
23.433 (M)
60.
Construction of External Infrastructure in Sector H-10 (IIUI), Islamabad.
7.421 (M)
61.
Rehabilitation of MR-II, NESCOM to I.J Principle Road, Sector I-11, Islamabad.
19.976 (M)
62.
Development Works/VRs in Sector I-11/1. (Vacated from Kachi Abadi), Islamabad.
8.634 (M)
63.
Rehabilitation of Approach Road from G.T Road to Hajj Complex, Sector I-14, Islamabad
0.741 (M)
64.
Construction of 3 Nos Remaining VRs in Sector I-16, Islamabad.
0.343 (M)
65.
Rehabilitation of damaged sewerage line St. 10 Plot No. 47 to 86 Sector I-9/2 & 3, Islamabad.
2.566 (M)
66.
"Development of Sector D-12, Islamabad "
2067.000 (M)
67.
Construction of Precast boundary wall b/w Sector D-12 & D-13 at Islamabad
35.376 (M)
68.
Protection of CDA's acquired land in Islamabad.
172.073 (M)
69.
Development of Sector C-15 Islamabad(Phase-I) (Construction of MRs, SRs, Plot-side, drainage work & Culverts).
4548.627 (M)
70.
Construction of 2nd carriageway from roundabout of Service Road (West) Sector G-10 to Khayaban-e-Iqbal, Islamabad
Rs.235,842,324